%% PQC Integration — Work Package Gantt Chart (24 Months) %% Proposal: €2.8M HORIZON-CL3-2025-CS-ECCC-06 %% Submission Deadline: 2025-12-15 %% Project Duration: M1 (2026-02) to M24 (2028-01) gantt title PQC Integration Work Plan — 24 Months (TRL 4→6) dateFormat YYYY-MM axisFormat %Y-%m section WP1 — Governance Framework D1.1 Requirements & Use Cases :wp1_d1, 2026-02, 3M D1.2 Architecture Specification :wp1_d2, after wp1_d1, 3M M1 Requirements Review :milestone, m1_review, 2026-06, 0d section WP2 — Proof & Anchoring D2.1 Sealer Implementation :wp2_d1, 2026-02, 6M D2.2 Verifier CLI Tool :wp2_d2, after wp2_d1, 3M D2.3 RFC-3161 TSA Integration :wp2_d3, after wp2_d2, 3M M2 Proof Engine Demo :milestone, m2_demo, 2026-12, 0d section WP3 — Ψ-Field & Observability D3.1 Ψ-Field Service v1.0 :wp3_d1, 2026-04, 6M D3.2 Observability Dashboard :wp3_d2, after wp3_d1, 4M D3.3 Anomaly Detection Module :wp3_d3, after wp3_d2, 2M M3 Ψ-Field Operational :milestone, m3_psi, 2027-04, 0d section WP4 — Federation & Trust D4.1 Federation Router v1.0 :wp4_d1, 2026-06, 6M D4.2 Testbed Deployment :wp4_d2, after wp4_d1, 4M D4.3 Trust Profile Specification :wp4_d3, after wp4_d2, 2M M4 Federation Live :milestone, m4_fed, 2027-06, 0d section WP5 — Pilots & Assessment Pilot Prep (France, Czech, Greece) :wp5_prep, 2026-12, 2M D5.1 Pilot Deployment Reports :wp5_d1, after wp5_prep, 6M D5.2 Standards Contributions (ETSI) :wp5_d2, after wp5_d1, 4M D5.3 Impact Assessment & Roadmap :wp5_d3, after wp5_d2, 2M M5 Final Review :milestone, m5_final, 2028-01, 0d section Critical Milestones Project Kickoff :milestone, kickoff, 2026-02, 0d Mid-Project Review (M12) :milestone, m12, 2027-02, 0d Final Review (M24) :milestone, m24, 2028-01, 0d section Integration Points Sealer → Ψ-Field Integration :crit, int1, 2026-10, 2M Federation → Pilot Handoff :crit, int2, 2027-02, 2M Standards Draft Freeze :crit, int3, 2027-10, 1M